  Front Page arrow FAQs arrow Research and Development arrow What drives the length of R and D projects?
 
What drives the length of R and D projects? Print
Page Index
What drives the length of R and D projects?
Page 2
Tip
For existing products, the farther that you move the product, or the bigger the change in the MTBF specification, the longer the project. However, the simulation makes a distinction between incremental improvement and quantum jump. If you move the product a very long way on the perceptual map, say six units, the project will complete in less than three years. An incremental project might take two years to move 3.0 units on the map.

For new products, all projects take at least one year, even if you make the specifications identical to an existing product, because it takes at least one year to buy the associated production capacity. This aside, project length is driven by the distance your new product is from existing products